Saudi Aramco Dew Point Control Unit (DPCU) Project

Delivery Time
2025
Service Mode
EPC
Project Owner
Saudi Aramco
Contract Mode: EPC

Time: 2020 – 2025

Project Description:

• Construction of hydrocarbon dew point control, propane refrigeration, and condensate acid gas removal units, along with modification of acid gas removal units. Natural gas processing capacity: 2,400 MMSCFD

• Wison undertakes Saudi Aramco's first modular project

• Comprising 72 modules, including pipe racks and process modules

• Executed deep in the desert, 650 km from the nearest city

• Supported by own construction team, with a peak workforce of over 3,000

• Brownfield shutdown modification completed ahead of schedule