Time: 2020 – 2025
Project Description:
• Construction of hydrocarbon dew point control, propane refrigeration, and condensate acid gas removal units, along with modification of acid gas removal units. Natural gas processing capacity: 2,400 MMSCFD
• Wison undertakes Saudi Aramco's first modular project
• Comprising 72 modules, including pipe racks and process modules
• Executed deep in the desert, 650 km from the nearest city
• Supported by own construction team, with a peak workforce of over 3,000
• Brownfield shutdown modification completed ahead of schedule
Message Inquiry