PetroChina Lanzhou Petrochemical 460 KTA Ethylene Cracking Furnace Burner Revamp Project

Delivery Time
2016
Service Mode
EM+PC
Project Owner
PetroChina Lanzhou Petrochemical Co.
Contract Mode: EM+PC
Time: 2005 – 2006
Project Description:
• Construction of a new 460 KTA ethylene unit, achieving on-spec product within 19 months
• Set a record for the shortest construction period of an ethylene plant in China — successfully commissioned 9 months ahead of schedule. The total construction period of 19 months was one-third shorter than the industry average
• Pioneered the EM+PC total service model in China