Home Solutions Project Case

Donghua Energy (Maoming) Alkane Resources Comprehensive Utilization Project

Delivery Time
2022
Service Mode
E; PDH Furnace: EPC
Project Owner
Donghua Energy (Maoming) Co., Ltd
Contract Mode:
• Alkanes Resource Utilization Project: FSR
• PDH Units: E
• Propane Dehydrogenation Heaters: EPC
Time: 2022
Project Description:
• Two 1.0 MMTA PDH Units (UOP NG PDH Technology)
• One PDH Propane Dehydrogenation Heater
• 2.0 MMTA Alkane Dehydrogenation Unit (including PSA Unit)
• 60 KTA Butadiene Extraction Unit
• 150 KTA Pyrolysis Gasoline Hydrogenation Unit
• 300 KTA LDPE/EVA Unit
• 2×650 KTA FDPE Units
• 500 KTA HDPE Unit