SATORP Refinery Train-2 DBN Project

Delivery Time
2020
Service Mode
PC
Project Owner
Kellogg Brown and Root Saudi Ltd. Co.
Contract Mode: PC
Time: 2018 – 2020
Project Description:
• Increased Train 2 capacity to 120% of the original design (from 200,000 BPSD to 240,000 BPSD), covering atmospheric and vacuum distillation, delayed coking, catalytic cracking, selective hydrogenation, hydrocracking, saturated and unsaturated gas treatment, etc.
• Undertaken in exclusive partnership with KBR for the Saudi Aramco / Total joint venture SATORP project